Overview

A selection of our key projects to date are detailed below, as you can see from this we cover a diverse scope of works for a broad range of applications. Please do not hesitate to contact us or email if you wish to find out more information about these specific projects and any other services we can offer.

 

Project

Client

Details


BARD Offshore Windfarm – Germany

April 2012 – Present

NSW

assisting NSW with 80no. 33kV Terms (power & fibre)

Camberley and Bracknell – 132kV Cable Installation

March 2012 – Present

ABB

3.0km 132kV Cable Installation including allcivils56no. 132kV Nexans Terminations (GIS and AIS)2no. 132kV Nexans Straight Joints +Joint Bay constructionFull-time Project Management

LondonArray Offshore Windfarm

July 2011 – Dec 2012

Visser

& Smit Hanab

175no. 33kV Terms. Full-time Project Management

Brick Lane – Temporary Sub -station relocation

Nov 2011

HVMS

LV and HV plinth construction, LV and HV cable routing including civils and cable laying, LV and HV jointing, 11kV

Creyke Beck – 132kV Jointing

April – Sept 2011

Morrisons

35no. ABB 132kV Terms + 4no. ABB 132kV Straight Joints

Pelamis Wave Hub Offshore

August 2011

Offshore Marine Management

33kV Closing Joint

Manchester 132kV Ericsson Oil Transition Jointing

March – May 2011

Murphy Group

4 no. Ericsson transition joints (fluid to XLPe)

Wakefield B – 132kV Jointing

March – Aug 2010

Morrisons

31no. ABB 132kV Terms. + 4no. ABB 132kV Straight Joints

Thanet Offshore Wind Farm

Jan 2010 – Jan 2011

Sub

Ocean Group

100no. 33kV Nexan Terms. + Jointing, Terms. For 132kV offshore platform

 

Please look at our case studies for an in depth look at some of our major projects.